How long a kitchen remodel takes
Updated 2 min read
How long a kitchen remodel takes
It depends mostly on how much of the kitchen changes. Published figures (market data, not our schedule) put a cosmetic update at one to two weeks of work and a full rebuild at two to three months, with most kitchen remodels somewhere around six to ten weeks.
| What changes (Angi, market data) | Published duration |
|---|---|
| Cosmetic: painted cabinets, a new backsplash | 1–2 weeks |
| Midrange: new cabinets, countertops and appliances | 4–8 weeks |
| Extensive: layout changes, walls moved or removed, everything new | 8–12 weeks or more |
The phases
| Phase (Angi, market data) | Published duration |
|---|---|
| Planning and design | 2 weeks to 3 months |
| Permits | 2–4 weeks |
| Demolition | 1–2 weeks |
| Construction | 8–12 weeks |
| Inspections and walkthrough | 2–4 weeks |
The phase figures describe a full remodel; a smaller job skips some of them. A cosmetic update usually needs no permit and no inspections at all.
What sets the pace
The order of the work is fixed: plumbing, wiring and any wall changes first, then cabinets, then countertops, then the backsplash and fixtures. Stone countertops are measured for cutting only once the cabinets are set and level, so the counters can't arrive before the cabinets are in.
Custom cabinets and counters are made to order, and Angi notes they can bring manufacturing delays; prefabricated pieces move faster.
What changes the number
- Moving the sink or range, or a load-bearing wall
- it adds rough-in work and, in North Carolina, a permit and its inspections.
- Custom cabinets or counters
- made to order, so their lead time sets the calendar.
- What's behind the walls
- old wiring, a leak or an uneven floor found at demolition is fixed before anything new goes in.
- Deliveries
- appliances and materials that arrive late hold up the trades waiting on them.
Permits and inspections
In a single-family home, cosmetic work usually needs no permit. Moving a drain, adding a fixture, running a new circuit or changing a load-bearing wall does, whatever it costs. Our permit guide explains the rules. In Mecklenburg County the building, plumbing, electrical, and heating and air conditioning parts each have their own permit and inspections.
Living without a kitchen
For most of a remodel the kitchen can't be used. We plan a temporary setup with you before demolition, so the household keeps working while the room is rebuilt.
Your own timeline
How long yours takes depends on the kitchen, so ask about it when you ask for your estimate. See kitchen remodeling and our kitchen remodel cost guide.
Sources (market data and rules as of November 2026): Angi, How Long Does a Kitchen Remodel Take? (updated July 8, 2026); N.C. Gen. Stat. § 160D-1110(c); Mecklenburg County Code Enforcement, Permitting.